Obama plan to 'Power Africa' gets off to a dim start
Barack Obama last year told a cheering crowd in Cape Town that a $7 billion plan to "Power Africa" would double electricity output on the world's poorest continent and bring "light where currently there is darkness".
A year later, the U.S. president's flagship project for Africa has already achieved 25 percent of its goal to deliver 10,000 megawatts of electricity and bring light to 20 million households and businesses, according to its annual report.
Continue...
But the five-year plan has not yet delivered the power.
Power Africa has not measured its progress by counting actual megawatts added to the grid but promises of additional power made in deals it says it helped negotiate
Obama's pledge to double power generation in Africa within five years looked highly ambitious from the start. Per capita electricity output in Sub-Saharan Africa has been flat for three decades because most promised power plants never get built.
"We're dealing with megawatts on paper, rather than on the grid," a second source working on the project said.
But the five-year plan has not yet delivered the power.
Power Africa has not measured its progress by counting actual megawatts added to the grid but promises of additional power made in deals it says it helped negotiate
Obama's pledge to double power generation in Africa within five years looked highly ambitious from the start. Per capita electricity output in Sub-Saharan Africa has been flat for three decades because most promised power plants never get built.
"We're dealing with megawatts on paper, rather than on the grid," a second source working on the project said.